建筑工地圍擋噴淋制作方式
來源:http://m.litoele.com/ 發(fā)布時(shí)間:2023-08-23
建筑工地圍擋噴淋是一種常見的建筑防護(hù)措施,通過使用噴淋系統(tǒng),可以降低建筑工地污染物和噪音的擴(kuò)散,減少工地塵土飛揚(yáng),改善施工環(huán)境,保護(hù)周邊居民健康和環(huán)境質(zhì)量。噴淋系統(tǒng)可以按照固定時(shí)間和噴淋量進(jìn)行程序控制,自動(dòng)化程度高,操作方便。
Construction site enclosure spraying is a common safety protection measure. By using a spraying system, the diffusion of pollutants and noise on construction sites can be reduced, dust can be reduced, the construction environment can be improved, and the health and environmental quality of surrounding residents can be protected. The spray system can be programmed according to a fixed time and spray volume, with a high degree of automation and easy operation.
在建筑工地圍擋噴淋的工程實(shí)施中,需要注意以下幾點(diǎn):
In the implementation of construction site enclosure spray engineering, the following points need to be noted:
,應(yīng)根據(jù)工地實(shí)際情況進(jìn)行勘測,確定噴淋管線和噴淋頭安裝位置,并考慮噴淋管的安裝高度、噴頭噴射方向角度和噴灑范圍,一般3-4米安裝一個(gè)噴霧頭,安裝時(shí)需車緊噴頭,高壓管安裝到位。
First of all, survey should be carried out according to the actual situation of the site to determine the installation position of the spray pipeline and the spray head, and consider the installation height of the spray pipe, the spray direction angle of the spray head and the spray range. Generally, a spray head is installed at 3-4 meters. During installation, the spray head needs to be tightened and the high-pressure pipe is installed in place.
其次,應(yīng)選用合適的噴淋設(shè)備和高壓管道材料,保證設(shè)備穩(wěn)定可靠,并注意采用防止凍裂的措施。
Secondly, appropriate spraying equipment and high-pressure pipeline materials should be selected to ensure the stability and reliability of the equipment, and measures to prevent frost cracking should be taken.
再次,噴淋水源應(yīng)確保供應(yīng)充足,并考慮配備水泵設(shè)備或蓄水池等外部水源保證正常使用。
Once again, the sprinkler water source should ensure sufficient supply and consider equipping external water sources such as water pump equipment or reservoirs to ensure normal use.
應(yīng)加強(qiáng)日常維護(hù)和管理,安排人員定時(shí)更換噴淋泵機(jī)油,避免缺失機(jī)油導(dǎo)致拉缸;注意清洗噴嘴、檢查管線和閥門等設(shè)備運(yùn)行情況,及時(shí)處理損壞和故障,保證系統(tǒng)正常運(yùn)行。
Daily maintenance and management should be strengthened, and personnel should be arranged to regularly replace the spray pump oil to avoid missing oil causing cylinder pulling; Pay attention to cleaning nozzles, checking the operation of pipelines and valves, and promptly handle damage and faults to ensure the normal operation of the system.